We previously reported the RAM upgrades that were completed during the first week. We knew we wouldn’t be able to continue at that pace because the remaining upgrades needed to take place over a much wider larger spread of buildings. Below is a summary of where we’re at and what we have left.
Week 1
- 4 locations
- 496 machines complete
Week 2
- 10 locations
- 238 machines complete
Week 3 (underway)
- 9 locations
- 249 machines
Week 4 (planned)
- 10 locations
- 70 machines